QA/QC, testing & handover

All capabilities

Inspection and documentation from mock-up to handover

Inspection and test plans define what is checked, when it is checked and against which acceptance criteria. Depending on the package, checks cover mock-ups, materials, fabrication tolerances and critical installation stages.

We record inspections and deviations, track close-out and compile as-built drawings, certificates and maintenance instructions for handover.

Illustrative scenario

Watertightness testing and closing out deviations

A façade mock-up is checked against the project test plan. The example shows how a finding is recorded and linked to final acceptance.

Curtain wall mock-up in a watertightness test chamber
Illustration generated for this scenario.
Control pointEvidenceScenario status
Before testingApproved method and mock-up condition recordReady for test
FindingWater ingress record and location on drawingOpen deviation
RetestPhoto of the correction and retest reportClosed following acceptance

The final report links the finding to the corrective action, the retest and the drawing revision released to fabrication.