Procurement aligned with approvals and the project programme
We define requirements for profiles, glazing, fixings and finishes from the technical information for each package. Samples and approvals are linked to ordering, processing and delivery dates.
Deliveries are sequenced around fabrication needs and the availability of installation areas. We identify long-lead items early and maintain batch traceability.
Illustrative scenario
Procuring glazing with a bespoke ceramic frit
Finalising the frit affects purchase release and delivery by zone. The matrix identifies the information needed to release each stage.

| Control | Prerequisite | Next action |
|---|---|---|
| Sample | Frit colour and density approved | Record the approved sample |
| Order | Dimensions, build-up and item codes confirmed | Release each batch |
| Delivery | Receiving sequence and labelling confirmed | Check the batch against the delivery note |
Item-level identification lets the team trace any shortfall or replacement to the affected zone.